Q-2, r. 23.1 - Regulation respecting the environmental impact assessment and review of certain projects

Full text
2. The projects listed in Schedule 1 are subject to the environmental impact assessment and review procedure provided for in subdivision 4 of Division II of Chapter IV of Title I of the Act, to the extent provided therein, and must be authorized in advance by the Government.
A project is subject to the procedure regardless of the number of persons who are proponents of the project.
O.C. 287-2018, s. 2.
In force: 2018-03-23
2. The projects listed in Schedule 1 are subject to the environmental impact assessment and review procedure provided for in subdivision 4 of Division II of Chapter IV of Title I of the Act, to the extent provided therein, and must be authorized in advance by the Government.
A project is subject to the procedure regardless of the number of persons who are proponents of the project.
O.C. 287-2018, s. 2.